Back to
ICESP VIII CONFERENCE PAPER ABSTRACTS C-5 SERIES

Held in Birmingham, AL, USA
May 14 - 17, 2001

The International Conference on Electrostatic Precipitation (ICESP) is the official conference of the International Society for Electrostatic Precipitation (ISESP).  

The following is a list of the Abstracts for the C-5 Series papers from the VIII ICESP Conference. 

C5-1 Pilot-Scale Evaluation of Positive Polarity for Hot-Side Electrostatic Precipitators
Wallis A. Harrison, Southern Company Services, Inc.
Kenneth M. Cushing, Southern Research Institute
Ralph F. Altman, Electric Power Research Institute

Abstract
Because of regulatory requirements to reduce SO2 emissions which became prevalent during the 1960s, utilities began looking to low-sulfur coal as a cost effective way to meet these requirements.  However, it became apparent that existing cold-side electrostatic precipitators were not going to perform well with these coals.  Engineers determined that “hot side” ESPs could be constructed at power plants upstream of air heaters where typical flue gas temperatures would be in the range of 550 to 850OF.  It was believed that, in this temperature range, the ash from most coals would have low resistivity.  However, as the number of hot-side ESPs in service grew, there developed a realization that these ESPs were having significant problems with low sulfur coal ash.  One of these poor performance problems was related to high resistivity.

In a hot-side precipitator, high resistivity, caused by the process know as sodium depletion, is typically time dependent.  The clean hot-side ESP performs well initially, but its performance degrades over a period of weeks or months.  One technique to deal with the high resistivity problem caused by sodium depletion is the use of positive polarity.  A number of tests have been conducted in laboratory settings to investigate the use of positive polarity; however, tests at pilot scale using actual flue gas have not been performed.  This is the subject of the study reported here.

To View Paper in PDF Format Click Here    
To go Back to ICESP Paper Page Click Here

C5-2 Electrical Re-Entrainment of Particles Deposited on Collecting Plate in Electrostatic Precipitator
Yoshihiko Mochizuki, Sadao Sakakibara & Hiroshi Asano, Hitachi Plant Engineering & Construction Co., Ltd.

Abstract
In an attempt to improve dust collecting performance of ESP, gas temperature in ESP was set around 90oC and electric resistivity was lowered to the order of 1010 to 1011cm.  Under these conditions, however, dust emission at ESP outlet was found much more, when collecting plate was hammered, than that under the other conventional conditions.  This is considered because cohesive force between dust particles is reduced for some reason.  In a bid to reveal the precise mechanism, authors identified three main forces affecting dust particle, namely Van der Waals force, Johnsen-Rahbek force and electrostatically induced force (Coulomb’s force by electrostatically induced charge), and scientifically studied balance among the three.  A series of experiments were also performed to find out how dust particle deposited on collecting plate was released into the air.  As a result, wide-spread dust particle release is more likely to occur as electric resistivity and current density drop.  It is also found that wide-spread dust dispersion mainly takes place on collecting plate in the middle of pitch between discharge wires, in the middle of pitch between spines and just beneath discharge frame because current density is kept low at these points.

To View Paper in PDF Format Click Here  
To go Back to ICESP Paper Page Click Here

C5-3 Development and Demonstration of ROPE – A New Pulse Energization System for Electrostatic Precipitators
Mark S. Berry and Wallis A. Harrison, Southern Company Services
Duane H. Pontius, Southern Research Institute
W. Ray Cravey, Alpha-Omega Power Technologies, Inc.

Abstract
No Abstract available

To View Paper in PDF Format Click Here 
To go Back to ICESP Paper Page Click Here

C5-4 An Investigation Into the Use of Electrode Mass Measurement To Optimize an Electrostatic Precipitator Unit
Shaun Pershad, Eskom Enterprises Technology Services International

Abstract
The paper details the investigation into the use of collecting electrode (CE) mass measurement to optimize a full scale electrostatic precipitator (ESP) unit, Initially, work was done at Eskom’s Hendrina Power Station, but due to problems experienced, further testing and experimentation had to be done at another test ESP unit.  The work at Hendrina Power Station showed that the research concept was viable and solutions were found to some of the problems experienced.  The present test unit is located at Eskom’s Lethabo Power Station situated in the Free State province of the Republic of South Africa (RSA).  This coal-fired power plant consists of six boiler units, each generating 620 MW. Each boiler is serviced by four rigid frame, Rothemuhle ESP casings in parallel, each consisting of seven fields in series, with a specific collecting area of 191.6 s/m and an aspect ration of 2.4.  The coal burnt at Lethabo can be considered as “difficult” coal – high ash content (up to 42%), highly resistive (in excess of 1013 ohm.cm) and low sulphur (0.6%).

One ESP casing was chosen for experimentation and load cells were installed in each field to provide an on-line, real-time, indication of the ESPs operational behavior.  An opacity monitor was installed on the outlet duct.  It was correlated against mass emission by iso-kinetic measurements.  ESP collection patterns were measured and trended against varying boiler conditions.  ESP collection rates and corresponding re-entrainment effects were also successfully measured.  Rapping optimization was approached on two fronts – emissions as well as wear and tear reductions.  The experimental set-up is being tested for total ESP optimization as well as automated operation and control.  Results to date show an emission reduction of 133 mg/Sm3 down to an operating level of 110 mg/Sm3. Rapping induced wear and tear has been potentially reduced by 90%.

This work has also facilitated the development of a generic rapping optimization procedure for use with other Eskom ESP units and the correlation of other ESP investigative and research projects with real plant data.  Following this success, the technique can now be recommended for implementation on other existing ESP units, for new units that may be built in the futre, and for units that are to be rebuilt or upgraded.

To View Paper in PDF Format Click Here
To go Back to ICESP Paper Page Click Here



Last updated: February 27, 2010.
Copyright © 1999 TRK Engineering Services, Inc. All rights reserved.
For more information contact: TRK Engineering Services - 95 Clarks Farm Road - Carlisle, MA 01741 - Telephone: 978-287-0550 - Fax: 978-287-0569 - email: trkeng@apcnetwork.com