|
C5-1
Pilot-Scale Evaluation of Positive Polarity for Hot-Side
Electrostatic Precipitators
Wallis
A. Harrison, Southern Company Services, Inc.
Kenneth M. Cushing, Southern Research Institute
Ralph F. Altman, Electric Power Research Institute
Abstract
Because of regulatory requirements to reduce SO2
emissions which became prevalent during the 1960s, utilities began
looking to low-sulfur coal as a cost effective way to meet these
requirements. However,
it became apparent that existing cold-side electrostatic
precipitators were not going to perform well with these coals.
Engineers determined that “hot side” ESPs could be
constructed at power plants upstream of air heaters where typical
flue gas temperatures would be in the range of 550 to 850OF.
It was believed that, in this temperature range, the ash from
most coals would have low resistivity.
However, as the number of hot-side ESPs in service grew,
there developed a realization that these ESPs were having
significant problems with low sulfur coal ash. One
of these poor performance problems was related to high resistivity.
In a hot-side precipitator, high resistivity, caused by the process
know as sodium depletion, is typically time dependent.
The clean hot-side ESP performs well initially, but its
performance degrades over a period of weeks or months.
One technique to deal with the high resistivity problem
caused by sodium depletion is the use of positive polarity.
A number of tests have been conducted in laboratory settings
to investigate the use of positive polarity; however, tests at pilot
scale using actual flue gas have not been performed.
This is the subject of the study reported here.
To View Paper in PDF Format Click Here
To go Back to ICESP Paper Page Click
Here
|
|
C5-2
Electrical Re-Entrainment of Particles Deposited on Collecting Plate
in Electrostatic Precipitator
Yoshihiko
Mochizuki, Sadao Sakakibara & Hiroshi Asano, Hitachi Plant
Engineering & Construction Co., Ltd.
Abstract
In an attempt to improve dust
collecting performance of ESP, gas temperature in ESP was set around
90oC and electric resistivity was lowered to the order of
1010 to 1011Ωcm.
Under these conditions, however, dust emission at ESP outlet
was found much more, when collecting plate was hammered, than that
under the other conventional conditions.
This is considered because cohesive force between dust
particles is reduced for some reason.
In a bid to reveal the precise mechanism, authors identified
three main forces affecting dust particle, namely Van der Waals
force, Johnsen-Rahbek force and electrostatically
induced force (Coulomb’s force by electrostatically induced
charge), and scientifically studied balance among the three.
A series of experiments were also performed to find out how
dust particle deposited on collecting plate was released into the
air. As a result,
wide-spread dust particle release is more likely to occur as
electric resistivity and current density drop.
It is also found that wide-spread dust dispersion mainly
takes place on collecting plate in the middle of pitch between
discharge wires, in the middle of pitch between spines and just
beneath discharge frame because current density is kept low at these
points.
To View Paper in PDF Format Click Here
To go Back to ICESP Paper Page Click
Here
|
|
C5-3
Development and Demonstration of ROPE – A New Pulse Energization
System for Electrostatic Precipitators
Mark
S. Berry and Wallis A. Harrison, Southern Company Services
Duane H. Pontius, Southern Research Institute
W. Ray Cravey, Alpha-Omega Power Technologies, Inc.
Abstract
No Abstract available
To View Paper in PDF Format Click Here
To go Back to ICESP Paper Page Click
Here
|
|
C5-4
An Investigation Into the Use of Electrode Mass Measurement To
Optimize an Electrostatic Precipitator Unit
Shaun
Pershad, Eskom Enterprises Technology Services International
Abstract
The paper details the
investigation into the use of collecting electrode (CE) mass
measurement to optimize a full scale electrostatic precipitator
(ESP) unit, Initially, work was done at Eskom’s Hendrina Power
Station, but due to problems experienced, further testing and
experimentation had to be done at another test ESP unit.
The work at Hendrina Power Station showed that the research
concept was viable and solutions were found to some of the problems
experienced. The present
test unit is located at Eskom’s Lethabo Power Station situated in
the
Free State
province of the Republic of South
Africa (RSA). This
coal-fired power plant consists of six boiler units, each generating
620 MW. Each boiler is serviced by four rigid frame, Rothemuhle ESP
casings in parallel, each consisting of seven fields in series, with
a specific collecting area of 191.6 s/m and an aspect ration of 2.4.
The coal burnt at Lethabo can be considered as
“difficult” coal – high ash content (up to 42%), highly
resistive (in excess of 1013 ohm.cm) and low sulphur
(0.6%).
One ESP casing
was chosen for experimentation and load cells were installed in each
field to provide an on-line, real-time, indication of the ESPs
operational behavior. An
opacity monitor was installed on the outlet duct.
It was correlated against mass emission by iso-kinetic
measurements. ESP
collection patterns were measured and trended against varying boiler
conditions. ESP
collection rates and corresponding re-entrainment effects were also
successfully measured. Rapping
optimization was approached on two fronts – emissions as well as
wear and tear reductions. The
experimental set-up is being tested for total ESP optimization as
well as automated operation and control.
Results to date show an emission reduction of 133 mg/Sm3
down to an operating level of 110 mg/Sm3. Rapping induced
wear and tear has been potentially reduced by 90%.
This work has also facilitated the development of
a generic rapping optimization procedure for use with other Eskom
ESP units and the correlation of other ESP investigative and
research projects with real plant data.
Following this success, the technique can now be recommended
for implementation on other existing ESP units, for new units that
may be built in the futre, and for units that are to be rebuilt or
upgraded.
To View Paper in PDF Format Click Here
To go Back to ICESP Paper Page Click
Here
|